Mumbai Metro Line-3 is 80.6% complete




operate at 33.5 km Mumbai Metro Line-3Also known as the Aqua Line, is 80.6% complete, Mumbai Metro 3 said in a tweet.

The Aqua Line has 28 stations and is the first underground Mumbai Metro Rail. Divided into phases, Phase-1 operates from Aarey to BKC while Phase-2 operates between BKC to Cuffe Parade. While Aarey to BKC has achieved 86.4% completion, BKC to Cuffe Parade is 76% complete.

Phase-1 of Aqua Metro is expected to be operational by December 2023.

As on March 31, 2023, Aqua Line’s total civil work is 92.2% complete, total system work is 49% complete, overall station construction is 89.2% complete, depot work is 59.5% complete, The mainline track work is 58.5% complete and the tunneling work is 100% complete.

Phase wise break up of project completion

Mumbai Metro 3 Phase-I Completion Status

Mumbai Metro 3

Source: Mumbai Metro 3 Twitter

Mumbai Metro 3 Phase-II Completion Status

Mumbai Metro 3

Source: Mumbai Metro 3 Twitter

Mumbai Metro 3

Source: Mumbai Metro 3 Twitter

Have a question or perspective on our article? We would love to hear from you.

Write to our Editor-in-Chief Jhumur Ghosh at jhumur.ghosh1@housing.com

Was this article helpful?

  • ,0,

  • ,0,

  • ,0,


recent podcasts






Join The Discussion

Compare listings

Compare